Building permit Outbuilding Demolition

Demolition: outbuilding in Sectorul 1

Sectorul 1, București Latest act: 5 Sep 2017

About the works

Building type
Outbuilding
Works
Demolition
Works on the plot
4
Issued by
Primăria Sectorului 1 al Municipiului București

The building permit no. 85/16/C was issued on 5 September 2017 by Primăria Sectorului 1 al Municipiului București. The first act in the register is the planning certificate no. 89/11/C, of 26 January 2017. 222 days passed between the first act and the last.

Path through the register

  1. 26 Jan 2017 Planning certificate no. 89/11/C Primăria Sectorului 1 al Municipiului București
  2. 5 Sep 2017 Building permit no. 85/16/C Primăria Sectorului 1 al Municipiului București

What you can unlock

Address protected Near the site
Beneficiary protected Full access

They open in your account when you are within 300 m of the site, or after an approved photo. People's names show only with full access.

On the same plot

3 more works

The area

Sectorul 1

The exact place shows on the map, in your account.

Open the map
All the sites here