Technical planning committee
Not yet permitted
Extension
Extension in Sectorul 1
Sectorul 1, București Latest act: 8 Oct 2026
About the works
- Works
- Extension
- Height regime
- S+P+2E
- Floors above ground
- 2
- Works on the plot
- 12
- Issued by
- Primăria Sectorului 1 al Municipiului București
The technical planning commission's opinion no. 38608/2026 was given on 8 October 2026 by Primăria Sectorului 1 al Municipiului București. The first act in the register is the technical planning commission's opinion no. 38608/2026, of 2 July 2026. 98 days passed between the first act and the last.
Path through the register
- 2 Jul 2026 Technical planning committee no. 38608/2026 Primăria Sectorului 1 al Municipiului București
- 8 Oct 2026 Technical planning committee no. 38608/2026 Primăria Sectorului 1 al Municipiului București
What you can unlock
Address
protected
Near the site
Beneficiary
protected
Full access
Designer
protected
Near the site
Architect
protected
Full access
They open in your account when you are within 300 m of the site, or after an approved photo. People's names show only with full access.
On the same plot
11 more works- 28 Jan 2014 Certificate No works
- 5 Nov 2014 Certificate Demolition
- 7 Nov 2014 Certificate New build
- 27 Jul 2016 Certificate New build: retail
- 4 Aug 2016 Certificate Demolition
- 9 Sep 2016 Certificate New build
- 22 Dec 2016 Permit Demolition
- 27 Apr 2021 Certificate New build: apartments
- 4 Nov 2021 Permit New build: apartments
- 31 Oct 2025 Certificate New build
The area