Building permit
Public building
New build
New build: institutional in Craiova
Craiova, Dolj Latest act: 22 Nov 2023
About the works
- Building type
- Institutional
- Works
- New build
- Height regime
- S+D+P+4E+ETH
- Floors above ground
- 5
- Works on the plot
- 13
- Issued by
- Primăria Municipiului Craiova
The building permit no. 1195/2023 was issued on 22 November 2023 by Primăria Municipiului Craiova. The first act in the register is the planning certificate no. 1431/2023, of 1 August 2023. 113 days passed between the first act and the last.
Path through the register
- 1 Aug 2023 Planning certificate no. 1431/2023 Primăria Municipiului Craiova
- 22 Nov 2023 Building permit no. 1195/2023 Primăria Municipiului Craiova
What you can unlock
Address
protected
Near the site
Beneficiary
protected
Near the site
They open in your account when you are within 300 m of the site, or after an approved photo. People's names show only with full access.
Firms at this address
1 registered firm- protected, opens near the site Registered at the site's address Limited Liability Company 4120 · Lucrări de construcții a clădirilor rezidențiale și nerezidențiale Trading registered in 2017
On the same plot
12 more works- 2 Oct 2012 Permit New build: offices
- 20 Feb 2013 Certificate Extension: offices
- 25 Nov 2014 Permit Utilities
- 17 May 2019 Permit New build: outbuilding
- 29 Jul 2019 Certificate New build: house
- 10 May 2023 Certificate No works
- 26 Sep 2023 Permit Utilities: institutional
- 21 Sep 2023 Permit Demolition: institutional
- 27 Jun 2024 Permit Signage
The area
The exact place shows on the map, in your account.
Open the map