Building permit
No building
Utilities
Utilities in Constanța
Constanța Latest act: 9 Apr 2019
About the works
- Works
- Utilities
- Works on the plot
- 27
- Issued by
- Primăria Municipiului Constanța
The building permit no. 504/2019 was issued on 9 April 2019 by Primăria Municipiului Constanța. The first act in the register is the planning certificate no. 1932/2018, of 14 May 2018. 330 days passed between the first act and the last.
Path through the register
- 14 May 2018 Planning certificate no. 1932/2018 Primăria Municipiului Constanța
- 9 Apr 2019 Building permit no. 504/2019 Primăria Municipiului Constanța
What you can unlock
Address
protected
Near the site
Beneficiary
protected
Full access
Applicant
protected
Near the site
They open in your account when you are within 300 m of the site, or after an approved photo. People's names show only with full access.
Firms at this address
29 registered firms- protected, opens near the site Named on the acts Joint-Stock Company 3513 · Transportul energiei electrice Struck off
- protected, opens near the site Registered at the site's address Limited Liability Company 7490 · Alte activități profesionale, științifice și tehnice n.c.a. Trading registered in 2020
- protected, opens near the site Registered at the site's address Limited Liability Company 4120 · Lucrări de construcții a clădirilor rezidențiale și nerezidențiale Trading registered in 2023
and 26 more
On the same plot
26 more works- 12 Apr 2007 Permit Utilities
- 20 Feb 2013 Permit Utilities
- 10 Oct 2017 Permit Utilities
- 31 Aug 2018 Permit Regularisation: apartments
- 20 Aug 2020 Permit Utilities: apartments
- 17 Sep 2019 Permit Alteration: retail
- 16 Dec 2019 Certificate Regularisation: house
- 17 Jan 2020 Certificate Signage
- 29 Mar 2023 Permit Extension
The area
The exact place shows on the map, in your account.
Open the map