Building permit
Apartment block
New build
New build: apartments in Constanța
Constanța Latest act: 4 Mar 2013
About the works
- Building type
- Apartments
- Works
- New build
- Height regime
- S+P+8E
- Floors above ground
- 8
- Homes
- 46
- Works on the plot
- 21
- Issued by
- Primăria Municipiului Constanța
The building permit no. 270/2013 was issued on 4 March 2013 by Primăria Municipiului Constanța. The first act in the register is the planning certificate no. 2674/2012, of 1 October 2012. 154 days passed between the first act and the last.
Path through the register
- 1 Oct 2012 Planning certificate no. 2674/2012 Primăria Municipiului Constanța
- 4 Mar 2013 Building permit no. 270/2013 Primăria Municipiului Constanța
What you can unlock
Address
protected
Near the site
Beneficiary
protected
Full access
They open in your account when you are within 300 m of the site, or after an approved photo. People's names show only with full access.
Firms at this address
19 registered firms- protected, opens near the site Named on the acts Limited Liability Company 7120 · Activități de testări și analize tehnice Trading registered in 2001
- protected, opens near the site Named on the acts Limited Liability Company 4299 · Lucrări de construcții ale altor proiecte inginerești n.c.a Trading
- protected, opens near the site Registered at the site's address Limited Liability Company 9313 · Activități ale centrelor de fitness Trading registered in 2025
and 16 more
On the same plot
20 more works- 16 Jan 2008 Permit Extension: house
- 2 May 2007 Certificate Extension: industrial
- 4 Mar 2008 Certificate Demolition: house
- 17 Jun 2008 Certificate New build: apartments
- 11 Mar 2009 Certificate New build: apartments
- 18 Jul 2014 Permit Alteration: apartments
- 25 Feb 2014 Certificate No works
- 6 Jan 2015 Permit Utilities
- 21 Aug 2015 Permit Utilities
The area
The exact place shows on the map, in your account.