Building permit
Public building
New build
New build: institutional in București
București Latest act: 28 Mar 2022
About the works
- Building type
- Institutional
- Works
- New build
- Works on the plot
- 11
- Issued by
- Primăria Sectorului 3 al Municipiului București
The building permit no. 104 was issued on 28 March 2022 by Primăria Sectorului 3 al Municipiului București. The first act in the register is the planning certificate no. 1424, of 27 December 2021. 91 days passed between the first act and the last.
Path through the register
- 27 Dec 2021 Planning certificate no. 1424 Primăria Sectorului 3 al Municipiului București
- 28 Mar 2022 Building permit no. 104 Primăria Sectorului 3 al Municipiului București
What you can unlock
Address
protected
Near the site
Beneficiary
protected
Full access
They open in your account when you are within 300 m of the site, or after an approved photo. People's names show only with full access.
On the same plot
10 more works- 4 Feb 1991 Permit Alteration: institutional
- 15 Dec 2020 Permit Alteration: institutional
- 21 Nov 2018 Permit Alteration: institutional
- 18 Mar 2020 Certificate Planning certificate
- 17 Mar 2022 Certificate Alteration: institutional
- 30 Jun 2023 Permit Alteration: institutional
- 23 May 2023 Certificate Alteration: institutional
- 7 Feb 2024 Certificate New build: institutional
- 6 Jul 2026 Certificate New build: institutional